Construction Activities for the week of February 12, 2016

This Week’s Construction Activities

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck

Performing Arts Center

  • Commenced Waterproofing on North Wall: Grid Line W1.
  • Completed Slab on Grade Prep and Placement: Phase 4, Gridlines W1-W3 & WA-WD.
  • Commenced 2nd Lift Wall Forms and Placement: Phase 4, W1-W3 & WA-WD.
  • Continue Spread Footing and Grade Beam Excavation, Resteel, and Placement: Gridline Wd-Te.5 &X1-Y7.
  • Commenced Waterproofing & Back Fill on North Wall: W1 Line.
  • Completed Drilled Piers: 80A, 80B, and 83

Building

  • Continued Deep Foundation Installation at Office Building: Grid Line R1-R2 Line.
  • Continued O8 Grid Line Excavation

Parking Deck

  • Continued Footings at Southwest Private Deck: Grid-lines P7-P11.
  • Installed Footings along Grid Line: P6.
  • Continued Controlled Rock Blasting in CIP Parking Deck: 8-P2.4 & PG-PH
  • Continue Shotcrete and Tiebacks at East and West Deck: Grid Line PH-PS & P1-P6 and TE-PJJ and O8-P6

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE
  • Completed Existing Wall Demo at Mount Vernon HWY NE
  • Dirt Stockpile in at NW Corner of Site ongoing.

 

Next Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

 

Performing Arts Center

  • Commence Excavation & Pouring of Footing: Along O8 line.
  • Forming Vertical Wall, Resteel, and Placement: Grid-line O8 between TC—TA
  • Continue Gravel Back Fill & Installation of Waterproofing Along North Wall: W1 line.

 

Building

  • Continue Deep Foundation Installation at Office.
  • Continue Excavation of O8 Line

Parking Deck

  • Continue Footings at Southwest Private Deck: Gridline PA-PG Line All Footings.
  • Commence Additional Deep Foundation Drilled Piers: Gridline PCC-PJJ Line
  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PCC-PJJ Zone
  • Continue Shotcrete and Tiebacks at East and West Deck: Grid Line: PCC—PJJ.
  • Mobilize Precast Erection Crane.
  • Commence Under Drain Installation.

 

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Complete Dirt Stockpile in at NW Corner of Site.

Screen Shot 2016-02-12 at 8.11.19 AM Screen Shot 2016-02-12 at 8.11.10 AM Screen Shot 2016-02-12 at 8.11.03 AM Screen Shot 2016-02-12 at 8.10.54 AM Screen Shot 2016-02-12 at 8.10.46 AM

Construction Activities for the week of February 5, 2016

Construction Activities Impacting Traffic Flow:

 A lane closure is underway on the northern-most lane on Johnson Ferry Road, beginning at Ferry Drive and ending just before Sandy Springs Circle. The lane will be closed Monday through Friday between the hours of 9 a.m. and 4 p.m.  Flagmen will direct the traffic flow at that closure, with the closure expected to be in effect through the month, weather permitting.

Message boards will be in place, and motorists are urged to plan for a slower pace and use added caution when driving in that area.

The traveling public is encouraged to check the City’s Road Work Advisory page found on the City’s website (shortcut: http://spr.gs/roadwork) and also available through the Sandy Springs Works mobile app (free in the app store).

This Week’s Construction Activities

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck

Performing Arts Center

  • Completed Deep Foundation Installation at PAC: Phase 5, Gridline Y6-W3 & WD-TE.5
  • Completed 1st Lift Wall Pour: Phase 3 & 4, Gridlines WD-TE.5 and TO-Z2
  • Completed Elevator Wall Pour: O5-W3 & PAA-WA
  • Commenced Spread Footing Excavation: Gridlines TC.2-TD.5 & X1-Y3
  • Continued Slab on Grade Prep: Gridlines W1-W3 & WA – WD

Building

  • Continued Deep Foundation Installation at Office Building: Grid Line OB-RA at O1-O4.
  • Continued O8 Line Excavation.

Parking Deck

  • Continued Footings at Southwest Private Deck: Grid-line PA.1-PE.7 & P7-P11
  • Continued Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PN & P5-P7
  • Continue Shotcrete and Tiebacks at East and West Deck: Grid Line PH-PS & P1-P6 and TE-PJJ and O8-P6

Other

  • Continued Georgia Power Trenching at Mount Vernon HWY NE
  • Commenced Existing Wall Demo at Mount Vernon HWY NE
  • Commenced Dirt Stockpile in at NW Corner of Site

 

Next Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.Performing Arts Center
  • Complete Slab on Grade Prep and Placement: Phase 4, Gridlines W1-W3 & WA-WD.
  • Commence 2nd Lift Wall Forms and Placement: Phase 4, W1-W3 & WA-WD.
  • Continue Spread Footing and Grade Beam Excavation, Resteel, and Placement: Gridlines WD-TE.5 & X1-Y7.

Building

  • Continue Deep Foundation Installation at Office Build-ing: Grid Line OB-RA at O1-O4.
  • Continue Excavation of O8 Line.

Parking Deck

  • Continue Footings at Southwest Private Deck: Gridline PA.1-PE.7 & P7-P11
  • Commence Additional Deep Foundation Drilled Piers: Gridline PA.1 at P8-P5.
  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PN & P5-P7
  • Continue Shotcrete and Tiebacks at East and West Deck: Grid Line PH-PS & P1-P6 and TE-PJJ and O8-P6

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE
  • Continue Existing Wall Demo at Mount Vernon HWY NE
  • Continue Dirt Stockpile in at NW Corner of Site

Screen Shot 2016-02-05 at 9.15.38 AM Screen Shot 2016-02-05 at 9.15.30 AM Screen Shot 2016-02-05 at 9.15.22 AM Screen Shot 2016-02-05 at 9.15.14 AM Screen Shot 2016-02-05 at 9.15.07 AM

Construction Activities for the week of January 29, 2016

This Week’s Construction Activities

Site/Structure

  • Completed Tower Crane Installation
  • Continued Site Excavation to Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck

Performing Arts Center

  • Commenced PAC Slab on Grade: Phase 4, Gridlines W1-T5 and WA-WC
  • Commenced PAC Wall Forms and Resteel: Phase 3 & 4, Gridlines WD-TE.5 and TO-Z2
  • Commenced Deep Foundation Installation at PAC: Phase 5, Gridline Y6-W3 & WD-TE.5
  • Continued Wall Forms and Resteel, at PAC: Gridlines W1-W3 & WA-WD

Building

  • Continued Deep Foundation Installation at Office Building: Grid Line OA-OE at O1-O4.

Parking Deck

  • Completed Deep Foundations at Southwest Private Deck: Grid Line P6.2 & PC.5
  • Continued Footings at Southwest Private Deck: Grid-line PA.1-PE.7 & P7-P11
  • Continued Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PN & P5-P7
  • Continued Shotcrete and Tiebacks at East and West Deck: Grid Line PA-PS & P1-P6 and TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

Next Week’s Construction Activities

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Commenced PAC Slab on Grade: Phase 4, Gridlines W1-T5 and WA-WC
  • Commenced PAC Wall Forms and Resteel: Phase 3 & 4, Gridlines WD-TE.5 and TO-Z2
  • Commenced Deep Foundation Installation at PAC: Phase 5, Gridline Y6-W3 & WD-TE.5
  • Continued Wall Forms and Resteel, at PAC: Gridlines W1-W3 & WA-WD

Building

  • Continue Deep Foundation Installation at Office Building: Grid Line OB-RA at O1-O4.

Parking Deck

  • Continued Footings at Southwest Private Deck: Grid-line PA.1-PE.7 & P7-P11
  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PN & P5-P7
  • Continue Shotcrete and Tiebacks at East and West Deck: Grid Line PH-PS & P1-P6 and TE-PJJ and O8-P6.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

Screen Shot 2016-01-29 at 8.04.09 AM Screen Shot 2016-01-29 at 8.04.02 AM Screen Shot 2016-01-29 at 8.03.55 AM Screen Shot 2016-01-29 at 8.03.45 AM Screen Shot 2016-01-29 at 8.03.38 AM

Construction Activities for the week of January 22, 2016

This Week’s Construction Activities

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Continue PAC Foundations in Phase 3 & 4: Gridline WD-TE.5 & W1-Z5
  • Completed Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Commenced Under Slab Plumbing and Electrical In-stallation at PAC: Gridline WA-WC & W1-W3
  • Continued Wall Resteel and Form Erecting at PAC: Gridline WA-WC & W1-W3

Building

  • Continued Deep Foundation Installation at Office Building: Grid Line OF-OK at O1-O4.

Parking Deck

  • Continued Deep Foundations at Southwest Private Deck: Grid Line P6.2 & PC.5
  • Commenced Footings at Southwest Private Deck: Gridline PA.1-PE.7 & P9-P11
  • Continued Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PA & P6-P7
  • Completed Tiebacks at Southwest Private Deck: Grid-lines P7—P11 & PA.1-PE.7
  • Continued Shotcrete and Tiebacks at East and West Deck: Grid Line PA-PS & P1-P6 and TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

Next Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Commence Deep Foundation Installation at Perform-ing Arts Center: Phase 5, Gridline Y6-W3 & WD-TE.5
  • Commence PAC Foundations in Phase 5: Gridline WA-WC & O5-O8 and WE-TF.7 & Z5-Z7
  • Continue Wall Forms, Resteel, and Installation at PAC: Gridlines W1-W3 & WA-WD

Building

  • Continue Deep Foundation Installation at Office Build-ing: Grid Line OA-OE at O1-O4

Parking Deck

  • Continue Deep Foundations at Southwest Private Deck: Grid Line P6.2 & PC.5
  • Continue Footings at Southwest Private Deck: Gridline PA.1-PE.7 & P7-P11
  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PN & P5-P7
  • Continue Tiebacks at West Deck: Gridlines PA-PS at P1
  • Continued Shotcrete and Tiebacks at East and West Deck: Grid Line PA-PS & P1-P6 and TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

Screen Shot 2016-01-22 at 5.19.55 PM Screen Shot 2016-01-22 at 5.19.45 PM Screen Shot 2016-01-22 at 5.19.39 PM Screen Shot 2016-01-22 at 5.19.27 PM Screen Shot 2016-01-22 at 5.19.19 PM

Construction Activities for the week of January 15, 2016

This Week’s Construction Activities

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Completed Brick Mock-Up

Performing Arts Center

  • Completed Deep Foundation Installation at Perform-ing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and Z4-Z6.
  • Continued PAC Foundations in Phase 3 & 4: Gridline WA-WC & O5-O8 and WC-TE.5 & Z1-Z2
  • Commenced Excavation of Phase 5 in Performing Arts Center: Gridline Y6-W3 & WD-TE.5
  • Completed Tower Crane Foundation and Set Pedestal
  • Continued Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Continued Wall Resteel and Form Erecting at PAC: Gridline WA-WC & W1-W3

Building

  • Continued Deep Foundation Installation at Office Building: Grid Line OF-OK at O1-O4.

Parking Deck

  • Commenced Deep Foundations at Southwest Private Deck: Grid Line P11 & PC.5
  • Continued Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PA & P1-P6
  • Completed Tiebacks at Southwest Private Deck: Grid-lines P7—P11 & PA.1-PE.7
  • Continued Shotcrete and Tiebacks at East and West Deck: Grid Line PA-PS & P1-P6 and TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

Next Week’s Construction Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Commence Deep Foundation Installation at Perform-ing Arts Center: Phase 5, Gridline Y6-W3 & WD-TE.5
  • Continue PAC Foundations in Phase 3 & 4: Gridline WA-WC & O5-O8 and WC-TE.5 & Z1-Z2
  • Continue Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Continue Wall Resteel and Form Erecting at PAC: Grid-line WA-WC & W1-W3

Building

  • Continue Deep Foundation Installation at Office Build-ing: Grid Line OD-OA at O1-O4.

Parking Deck

  • Continue Deep Foundations at Southwest Private Deck: Grid Line P6.2 & PC.5
  • Commence Footings at Southwest Private Deck: Grid-line PA.1-PE.7 & P9-P11
  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PA & P6-P7
  • Completed Tiebacks at Southwest Private Deck: Grid-lines P7—P11 & PA.1-PE.7
  • Continued Shotcrete and Tiebacks at East and West Deck: Grid Line PA-PS & P1-P6 and TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

 

Screen Shot 2016-01-15 at 4.30.58 PM Screen Shot 2016-01-15 at 4.30.48 PM Screen Shot 2016-01-15 at 4.30.42 PM Screen Shot 2016-01-15 at 4.30.34 PM Screen Shot 2016-01-15 at 4.30.24 PM

 

 

Construction Activities for the Week of January 8, 2016

Construction Activities Impacting Traffic Flow:

Beginning February 1, 2016, the northern-most lane on Johnson Ferry Road, beginning at Ferry Drive and ending just before Sandy Springs Circle, will be closed Monday through Friday between the hours of 9 a.m. and 4 p.m.  Flagmen will direct the traffic flow at that closure, with the closure expected to be in effect through the month, weather permitting.

Beginning February 15, 2015, one lane on Sandy Springs Circle, from Mt Vernon Road to Johnson Ferry Road, will close.   The lane closure will shift as crews work north-to-south along Sandy Springs Circle.    Access to the Springs Landing Shopping Center will remain available throughout this construction period.  Construction is part of a phased program taking place as part of the City Springs development project.

Message boards will be in place, and motorists are urged to plan for a slower pace and use added caution when driving in that area.

The traveling public is encouraged to check the City’s Road Work Advisory page found on the City’s website (shortcut: http://spr.gs/roadwork) and also available through the Sandy Springs Works mobile app (free in the app store).

This Week’s On Site Activities

Site / Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck

Performing Arts Center

  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and Z4-Z6.
  • Continued PAC Foundations: Gridline WA-WC & O5-O8
  • Commenced Tower Crane Foundation
  • Completed Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Commenced Wall Resteel and Form Erecting at PAC: Gridline WA-WC & W1-W3

Building

  • Continue Deep Foundation Installation at Office Build-ing: Grid Line OD-OK at O8-O4.

Parking Deck

  • Continued Controlled Rock Blasting in CIP Parking Deck: Grid Line PS-PG & P1-P6
  • Continued Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Completed Row 2 Tie-Backs at West Deck: Grid Line PA-PP & P1.
  • Commenced Row 3 Tie-Backs at SWP Deck: Grid Line P7—P11 & PA.1-PE.7
  • Commenced Shotcrete at East Deck: Gridlines TE-PJJ and Z7-O8

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

Next Week’s Activities

Site / Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Commence Brick Mock-Up

Performing Arts Center

  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and Z4-Z6.
  • Continued PAC Foundations: Gridline WA-WC & O5-O8
  • Commenced Tower Crane Foundation
  • Completed Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Commenced Wall Resteel and Form Erecting at PAC: Gridline WA-WC & W1-W3

Building

  • Continue Deep Foundation Installation at Office Build-ing: Grid Line OD-OK at O8-O4.

Parking Deck

  • Commence Deep Foundations at Southwest Private Deck: Grid Line P7—P11 & PA.1-PE.7
  • Commence Foundations at Southwest Private Deck: Grid Line P7—P11 & PA.1-PE.7
  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PG-PA & P1-P6
  • Complete Shotcrete and Tiebacks at Southwest Private Deck: Gridlines P7—P11 & PA.1-PE.7
  • Continue Shotcrete and Tiebacks at East and West

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

Screen Shot 2016-01-07 at 1.34.52 PM Screen Shot 2016-01-07 at 1.34.44 PM Screen Shot 2016-01-07 at 1.34.37 PM Screen Shot 2016-01-07 at 1.34.26 PM Screen Shot 2016-01-07 at 1.34.19 PM

Construction Activities for the Week of December 18, 2015

ACTIVITIES THIS WEEK:

Site / Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and TO-Z2.
  • Completed Deep Foundation Installation at Office Building: Grid Line PQ-PS & R6-R8.
  • »Continued Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continued Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continued Row 2 Tie-Backs at West Deck: Grid Line PA-PP & P1-P6.
  • Commenced Controlled Rock Blasting in CIP Parking Deck
  • Continued PAC Foundations and Underdrain System: Gridline WA-WC & T5-W3
  • Commenced PAC Foundation Pour: Gridline WA-WC & W1-W3
  • Commenced Drainage Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

ACTIVITIES NEXT WEEK

Site / Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.

Performing Arts Center

  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and Z4-Z6.
  • Continue PAC Foundations: Gridline WA-WC & O5-O8
  • Continue Underdrain Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3
  • Commence Wall Resteel and Form Erecting at PAC: Gridline WA-WC & W1-W3

Building

  • Continue Deep Foundation Installation at Office Build-ing: Grid Line P2-PV at O6.

Parking Deck

  • Continue Controlled Rock Blasting in CIP Parking Deck: Grid Line PS-PK & P1-P6
  • Continue Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continue Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Complete Row 2 Tie-Backs at West Deck: Grid Line PA -PP & P1-P6.
  • Commence Row 3 Tie-Backs at SWP Deck: Grid Line P7—P11 & PA.1-PE.7

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

Screen Shot 2015-12-17 at 12.51.23 PM Screen Shot 2015-12-17 at 12.51.14 PM Screen Shot 2015-12-17 at 12.51.07 PM Screen Shot 2015-12-17 at 12.50.57 PM

Construction Activities for the Week of December 11, 2015

THIS WEEK’S ACTIVITIES

We began pouring concrete at the site of the performing arts center this week, a noteworthy milestone.  The construction team created this video to demonstrate their ‘order of operations.’

 

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Completed H-Pile Installation in East Deck with Kelly Bar: Section 3, Grid Lines PFF- PJJ and P4-P6
  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and TO-Z2.
  • Continued Deep Foundation Installation at Office Building: Grid Line PQ-PS & R5-R8.
  • Continued Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continued Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Completed Row 2 Tie-Backs at Southwest Private Deck Shoring Walls: Grid Line P7—P11 & PA.1-PE.7.
  • Commenced Row 2 Tie-Backs at West Deck: Grid Line PA-PP & P1-P7
  • Commenced PAC Foundations and Underdrain Sys-tem: Gridline WA-WC & W1– T5

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

NEXT WEEK’S ACTIVITIES

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and TO-Z2.
  • Complete Deep Foundation Installation at Office Building: Grid Line PQ-PS & R6-R8.
  • Continue Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continue Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continue Row 2 Tie-Backs at West Deck: Grid Line PA -PP & P1-P6.
  • Commence Controlled Rock Blasting in CIP Parking Deck
  • Continue PAC Foundations and Underdrain System: Gridline WA-WC & T5-W3
  • Commence PAC Foundation Pour: Gridline WA-WC & W1-W3
  • Commence Drainage Pipe and Stone Installation at PAC: Gridline WA-WC & W1-W3

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

Screen Shot 2015-12-11 at 8.05.44 AM Screen Shot 2015-12-11 at 8.05.35 AM Screen Shot 2015-12-11 at 8.05.26 AM Screen Shot 2015-12-11 at 8.05.18 AM Screen Shot 2015-12-11 at 8.05.10 AM

Construction Activities for the Week of December 4, 2015

Activities This Week

Site/Structure

  • Continued Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continued H-Pile Installation in East Deck with Kelly Bar: Section 4, Grid Lines PW to PBB at P6
  • Continued Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 4, Grid Line WA—WC and T5-W3 and Phase 2, Grid Line TB.4 to TC.5 at TO
  • Continued Deep Foundation Installation at Office Building: Grid Line PQ-PS & R6-R8.
  • Continued Shotcrete at Southwest Private Deck, West Deck, and East Deck: Grid Line P7—P11 & PA.1-PE.7, PH-PS at P1/ PE-PS at P6, and T7-08 at TE.
  • Continued Shotcrete Prep in Southwest Private Deck, West Deck, and East Deck : Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6, and T7-08 at TE.
  • Completed Tie-Backs at West Deck and East Deck Shoring Walls: Grid Line PG-PH & P1-P0.1, and T7-08 at TE.
  • Began Row 2 Tie-Backs at Southwest Private Deck Shoring Walls: Grid Line P7—P11 & PA.1-PE.7.

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

 

Next Week’s Activities

Site/Structure

  • Continue Site Excavation To Drilled Pier Grade in Performing Arts Center, At Southwest Private Deck in Support of Shotcrete Wall Installation, and East Deck.
  • Continue H-Pile Installation in East Deck with Kelly Bar: Section 3, Grid Lines PFF- PJJ and P4-P6
  • Continue Deep Foundation Installation at Performing Arts Center Elevation 1080’: Phase 2 & 3, Grid Line TC.2-TE.5 and TO-Z2.
  • Continue Deep Foundation Installation at Office Build-ing: Grid Line PQ-PS & R6-R8.
  • Continue Shotcrete at Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Continue Shotcrete Prep in Southwest Private Deck and West Deck: Grid Line P7—P11 & PA.1-PE.7, PA-PS & P1-P6.
  • Complete Row 2 Tie-Backs at Southwest Private Deck Shoring Walls: Grid Line P7—P11 & PA.1-PE.7.
  • Begin Row 2 Tie-Backs at West Deck: Grid Line PA-PP & P1-P6.
  • Commence PAC Foundations and Underdrain System: Gridline WA-WC & W1– T2

Other

  • Continue Georgia Power Trenching at Mount Vernon HWY NE

Screen Shot 2015-12-03 at 2.07.18 PM Screen Shot 2015-12-03 at 2.06.41 PM Screen Shot 2015-12-03 at 2.06.10 PM Screen Shot 2015-12-03 at 2.05.51 PM Screen Shot 2015-12-03 at 2.05.37 PM